Pasadena Connecting Channel Plastered
access_time April 20 2016 05:39 PM remove_red_eye 1231
Reported by Nurito | Translated by Rizky Mawardi
Reported by Nurito | Translated by Rizky Mawardi
Pacuan Kuda Pulomas area, East Jakarta keeps being arranged towards Asean Games 2018. One of the efforts is dredging and installing plaster along Pasadena connecting channel.
Channel to be dredged and plastered is about 1.6 kilometer
Ahmad Yazied Bustomi, East Jakarta Head Sub-dept. of Water Management, admitted the project is implemented in front of Pacuan Kuda Pulomas.
“Channel to be dredged and plastered is about 1.6 kilometer,” he said, Wednesday (4/20).
30 PPSU Personnel Cleaned Pulomas DebrisAccording to him, plastering project is divided into two sides, west and east. Each side to be plastered is 800 meters with two meters of height above water surface and 50 cm into the channel bottom.
The project has been started since a month ago and it is targeted to complete this April.